Home

Hot Topics!

Upcoming Events

Overview Map

Geysers History

About GGA

GGA Board

Committees

Corporate Members

Membership

Newsletter

Scholarships

Contact us

Related Websites

GGA Hot Topics

Key accomplishments and emerging issues at The Geysers:

  • Lake County's Southeast Geysers Recharge Project continues its unprecedented success since its inception in September 1997, and Lake County plans additional recharge related projects.

  • The Geysers Recharge Project began pumping water from the City of Santa Rosa to The Geysers in December 2003. Approximately 11 million gallons of tertiary treated wastewater is pumped daily through the 41-mile pipeline.

  • EARTHQUAKES of varying magnitudes in The Geysers area continue to stir citizen concerns about the source of the activity and the prognosis of their effect.

     

LINKS TO GEOTHERMAL VIDEOS OF INTEREST
Geothermal Heats Up - KQED - QUEST - (November, 2008)

 

Geothermal Drilling Safeguards Imposed

By JAMES GLANZ Published: January 15, 2010, copyright The New York Times

The United States Energy Department, concerned about earthquake risk, will impose new safeguards on geothermal energy projects that drill deep into the Earth's
crust.

The new policy is being instituted after a project in California that used the new technology was shut down by technical problems and encountered community opposition, federal documents indicate.

The project, by Seattle-based AltaRock Energy, would have fractured bedrock and extracted heat by digging more than two miles beneath the surface at a spot called The Geysers, about 100 miles north of San Francisco. The company ran into serious problems with its drilling and faced accusations from scientists and local residents that it had not been forthcoming enough about the earthquake risk. AltaRock denied those accusations.

The documents, provided to The New York Times by the Energy Department, indicate that the Geysers project has run through $6 million in federal financing in several unsuccessful efforts to drill to the necessary depth. As a result, the Energy Department “considers the project in the Geysers to be concluded,” according to a letter addressed to Henry A. Waxman , the California Democrat and chairman of the House committee on Energy and Commerce.

The letter, dated Dec. 30, is signed by Cathy Zoi, an assistant energy secretary. The Times reported in early December that AltaRock had removed its drill rig from the site and informed the department that the project would be abandoned, but the company had refused to comment publicly.

In a second document dated Sept. 11, 2009, but not previously disclosed, the department concluded that earthquakes that would have been set off by the AltaRock project would “not have a significant impact on the human environment.” And in another endorsement of the company, the department later awarded AltaRock $25 million to try a similar project at the Newberry Volcanic Monument near Bend, Ore.

The Oregon project was one of 123 geothermal projects in 38 states that received $338 million through the Obama administration's economic stimulus package , Ms. Zoi said in the letter.

Two seismic experts who read the documents said the message about the perils and potential of geothermal energy was unclear. But Ernie Majer, a seismologist and deputy director of the Earth Science Division at Lawrence Berkeley National Laboratory in California, said that the new standards were a welcome development. The letters show that the department “is being ultra-careful about any induced seismicity,” he said, referring to earthquakes triggered by humans.

Among the new safeguards are requirements that projects monitor ground-motion sensors and other data and have an approved plan to shut down if earthquakes induced by the drilling are too powerful. Companies must also file estimates of expected earthquake activity and submit project proposals to outside experts for a review of the risks and the likelihood of success.

Ms. Zoi conceded in her letter that the department's findings were “likely to have little practical effect on the AltaRock project at the Geysers,” because the project apparently no longer exists. But she said that the defunct project and the findings “have provided valuable lessons.”

In a statement responding to questions on the documents, Stephanie Mueller, a spokeswoman for the department, said that those lessons “will help the United States succeed in safely harnessing geothermal energy.”

Donald O'Shei, AltaRock's chief executive, said in an e-mail message that the company was pleased by the department's finding that the Geysers project would not have had a significant impact on people in the area.

Regarding the Oregon project, Mr. O'Shei said that the company was “working on an initial planning process for the technical, permitting, and community education and outreach aspects of the project.”

Mr. O'Shei added, “Bend is located approximately 22 miles away from the demonstration site, which is in a sparsely populated area to the west of Newberry in central Oregon.”

Copyright, The New York Times

 

Project aims to bring new life to wells at The Geysers
JEFF KAN LEE/The Press Democrat
By GLENDA ANDERSON - THE PRESS DEMOCRAT - Published: Friday, December 25, 2009

Two defunct steam-generating wells at The Geysers will be revived this summer as part of a federally-supported project aimed at expanding and enhancing geothermal energy sources.

“The government is looking for these types of projects,” said Mike Rogers, vice president of operations for Calpine's geothermal project at The Geysers steam fields, which straddle Sonoma and Lake counties.

The project is funded in part by the Department of Energy, which has funneled more than $400 million into its geothermal program this year. It will contribute $5.7 million toward the cost of Calpine's project, estimated at almost $12 million, according to energy department documents.

The Lawrence Berkeley National Laboratory is participating in the project.

Water will be injected into one of the two reopened wells to enhance naturally occurring underground steam production, as is done at Calpine's other electricity-generating wells at The Geysers, Rogers said.

The second well will be used to closely monitor and record the effects of the water infusion into hot rock formations beneath the earth's surface, he said.

Both wells are located in the northwestern portion of The Geysers fields in Sonoma County.

After a period of time, the functions of the two demonstration wells will be switched, Rogers said.

The difference between the demonstration project and current operations is the level of monitoring, which will include tracing the steam's source, movement and effects, Rogers said.

“The overarching intent here is to give us the best approach for expanding into the northwest corner of The Geysers,” he said.

Like the existing wells, the demonstration wells are expected to generate seismic activity, most of it unfelt. They're not expected to generate significant quakes, like those triggered by a controversial 2005 project in Basel, Switzerland. In the Swiss project, a company drilled three miles deep and generated steam by fracturing hot bedrock
and then circulating water through it.

A proposal for similar drilling at The Geysers was halted this month by AltaRock Energy after the Swiss government permanently shut down the Basel operation.

Residents of Anderson Springs, a community of about 200 homes wedged in a narrow Lake County valley surrounded by geothermal wells, expressed relief that AltaRock had halted operations.

The valley is plagued by property-damaging earthquakes believed to be triggered by The Geysers' electricity generating wells.

Its residents also are pleased that Calpine is conducting its latest project some eight miles away from their homes. The study wells are located on the far northwestern section of The Geysers steam fields, which cover about 30 square miles.

“We certainly are supportive of their efforts to test these technologies in areas that are a lot further from the community because it's less likely to have an impact,” said Jeff Gospe, president of the Anderson Springs Community Alliance.
Copyright © 2009 PressDemocrat.com

Calpine Signs New Long-Term Power Contracts to Ensure California Continues to Receive Clean, Reliable Power

Fri Oct 30, 2009 HOUSTON--(Business Wire)--

Calpine Corporation (NYSE:CPN) today announced it has entered into several new power supply contracts with Pacific Gas and Electric Company (PG&E). Calpine has executed new contracts to replace existing contracts it signed with the State of California during the energy crisis, as well as to increase the supply of renewable power delivered to PG&E from The Geysers.

In response to the State of California`s program to manage the energy crisis of2000-2001, Calpine was the first power company to enter into long-term contracts with the State and was the first company to voluntarily renegotiate more favorable terms for the State. Now, in furtherance of the California Public Utilities Commission`s and the State`s policy objectives of removing the California Department of Water Resources (DWR) from its energy crisis role as the power purchaser of last resort, Calpine and PG&E have finalized contracts to replace two of these DWR contracts to ensure ratepayers continue to enjoy the benefits of Calpine`s clean, reliable, cost-effective and well-located power facilities. As part of this negotiation, Calpine and PG&E have agreed to upgrade the Los Esteros Critical Energy Facility, located in Silicon Valley, to operate in combined-cycle mode at an increased capacity and higher efficiency.

"Through these agreements Calpine is very pleased to assist PG&E in serving the changing generation needs in California," said Calpine President and Chief Executive Officer Jack A. Fusco. "We welcome the opportunity to work with PG&E to supply both incremental renewable power and flexible and reliable natural gas-fired generation necessary to integrate intermittent renewable energy supplies coming on-line in furtherance of the State of California`s 33 percent renewable goal."

These following agreements will be submitted to the California Public Utilities Commission by PG&E for approval:

Extension of Calpine Northern California Peaking Power Plant Contract

Calpine`s 11 peaking units, providing approximately 500 megawatts (MW), are highly dispatchable, reliable and are well located in Northern California. These power plants, which came on-line in 2002 and 2003, were under a power purchase agreement with the DWR which was due to expire in mid-2011. Calpine and PG&E have entered into a replacement contract whereby PG&E will enjoy greater dispatch flexibility for all 11 units through 2017 and for the seven Bay Area units through 2021.

Upgrade of the Los Esteros Critical Energy Facility

The Los Esteros Critical Energy Facility (LECEF), located in San Jose, California, was constructed and placed in operation by Calpine in 2003 pursuant to a power purchase agreement with DWR. In connection with the novation of the
existing DWR contract, which will expire at the end of 2012, Calpine and PG&E have negotiated a new agreement to facilitate an upgrade of LECEF from a 180 MW simple-cycle generation facility to a 300 MW (289 MW July peak) combined-cycle generation facility. In addition to the increase in capacity, the upgrade project will increase the efficiency and environmental performance of the plant by significantly lowering the heat rate.

Extension and Expansion of PG&E`s Contract for Renewable Power from Calpine`s Geysers Geothermal Facility

Calpine and PG&E have agreed to a significant extension of the term and an increase in the volume under the existing contracts for delivery of electricity from The Geysers geothermal facility. Calpine currently provides PG&E a total of 375 MW of power under two contracts through 2012 and 2014. The parties have agreed to increase the volume to 425 MW through 2017. From 2018 through the end of 2021, Calpine will supply PG&E 250 MW of renewable energy from The Geysers.

The extension and increases in volume under these new contracts will not only assist PG&E in meeting its renewable goals, but will provide Calpine with the resources required to continue its efforts to maintain and increase the energy output from The Geysers, the largest geothermal facility in the United States.



AltaRock Energy -- Updates EGS Demonstration Project Status with NCPA at The Geysers

September 2, 2009

AltaRock Energy Inc. announced it had suspended its drilling operations in the southeast Geysers on the Northern
California Power Agency (NCPA) leasehold. AltaRock had planned to redrill NCPA well E-7 into the felsite, the intrusive rock underlying
the Geysers steam reservoir, to a total depth of 12,000 ft as part of a DOE-funded Enhanced Geothermal Systems project to demonstrate the
ability to create multiple fracture zones in one well. Following the redrill, the plan was to inject at low temperature and pressure to
create multiple stimulated zones. E-7 was originally drilled in 1988 and was an active injector at the time of the workover.

An Environmental Assessment was completed, including an analysis of the risk of induced seismicity, for the Bureau of Land Management as part of NEPA/CEQA compliance for the project. The BLM issued a Finding of No
Significant Impact (FONSI) with mitigation for the project on June 9, 2009. The BLM and AltaRock are in the process of negotiating a protocol for mitigation of any potential impacts from the stimulation. Separate NEPA compliance is required for the DOE grant and that process is currently in review while AltaRock redesigns its drilling plan with input from NCPA.

AltaRock attempted to redrill E-7 three separate times from starting depths of 3202 ft, 1674 ft and 2733 ft. Each attempt reached a total depth in the range of 4100-4400 ft, before the drilling assembly became stuck due to the hole collapsing in the unstable serpentine and mélange. AltaRock is currently reviewing the reasons for the particularly unstable behavior of the formation below E-7. However, long term
injection into the area may have contributed to the problems. Drilling is an inherently risky business with high incidences of failure. The Geysers is an especially challenging and unique drilling environment because of the existence of serpentinized peridotite, which contains clays and fibrous material that will become unstable and collapse or flow when exposed to water over an extended period of time. Below the serpentine, the mélange (a jumble of large blocks of varied lithologies, including more serpentine) and fractured greywacke present
additional challenges. Lastly, reworking an existing well (as required by the DOE grant) limited the possible range of solutions to drilling and completion problems.

It is our hope that EGS power can impact the environmental and economic landscape of America by delivering baseload, carbon-free power. In cooperation with NCPA and the US Department of Energy, we are evaluating
possible paths forward at The Geysers and elsewhere for demonstrating our capabilities. Currently AltaRock has a portfolio of about 20 patent filings relating to EGS and is actively continuing to develop its proprietary technology in this area. We believe EGS is a clean,
renewable-energy alternative that holds the potential to significantly reduce our country's dependence on fossil fuels and create a more
sustainable future.
(Source: Susan Petty, AltaRock)


Department of the Interior Opens Renewable Energy Coordination Office in California to Speed Project Processing

October 9, 2009

Secretary of the Interior Ken Salazar and Bureau of Land Management Director Bob Abbey today officially opened a California Renewable Energy Coordination Office, one of several Interior initiatives to expedite the leasing and production of renewable energy resources on public lands in the West.

"These offices in California, Nevada, Arizona and Wyoming, along with our renewable permitting teams in six other western states, will help to swiftly complete application reviews on the most ready-to-go and environmentally
appropriate solar, wind, and geothermal projects on U.S. public lands," Salazar said. "In California the coordinating office will enable us to balance vital renewable energy development with the needed protection of sensitive resources in the California Desert Conservation Area."

The coordinating offices and teams, which also support the speedy permitting of power transmission projects on public lands, aim to reduce BLM's existing pending applications and use new procedures to expedite the leasing, production and delivery of renewable energy to consumers in less time than under current practices.

The BLM continues to experience a significant increase in private sector interest and applications for the development of wind, solar, and geothermal energy resources and associated electrical transmission systems on public lands. Currently BLM has received about 500 renewable energy project applications and the submissions are growing.

Of the solar and wind projects currently proposed, Salazar said, more than 5,300 megawatts of new capacity could be ready for construction by the end of 2010. That is enough to power almost 1.8 million homes. And project construction will create more than 48,000 jobs.

Salazar said the clean energy potential of these areas offer a significant opportunity to help realize President Obama's energy and climate change strategy to make fuller use of our domestic energy resources and create "green jobs" for local communities, while reducing our dangerous - and expensive - dependence on foreign oil.

"We have set aside 1,000 square miles of public lands in 24 Solar Energy Study Areas that the Department and BLM are evaluating for solar energy development across the West," Salazar said. "If developed, these tracts could generate nearly 100,000 megawatts of solar electricity." The Administration has invested $41 million in the President's economic recovery plan to facilitate a rapid and responsible move to large-scale production of renewables on public lands.

"With coordinated environmental studies, good land-use planning and zoning and priority processing, we can accelerate responsible renewable energy production and lay the foundation for a clean-energy economy for the 21st century," Salazar said.

The RECO Program Manager in the California office will be Greg Miller, a 21-year veteran of the BLM who began his career as a Wildlife Biologist and now manages the renewable energy program for the California Desert District.
He will lead a staff of 12 to 15 specialists at two BLM locations -- Palm Springs and Moreno Valley.

As virtual offices, the RECO staffers are located in different BLM offices within each state, working together through coordinated structures and leadership to speed all aspects of the application and permitting process. To lead the overall initiative, Salazar has established a National Renewable Energy Office at BLM's Headquarters in Washington D.C which includes a Renewable Energy Team Leader and a Program Manager for each of the renewable
energy and transmission programs.

The four Renewable Energy Coordinating Offices have identified 62 positions that will be filled with reassignments or new selections to support the
processing of renewable energy and transmission applications. Thirty-five additional renewable energy support staff have been identified for the BLM renewable permitting teams in the six western states of Colorado, Idaho, Montana, New Mexico , Oregon, and Utah.

 

Western GeoPower Announces Approval of Environmental Document and Conditional Use Permit
Wednesday, July 22, 2009

VANCOUVER, BRITISH COLUMBIA, Jul 22, 2009 (Marketwire via COMTEX) - Western GeoPower Corp. (TSX VENTURE:WGP) (FRANKFURT:WE6), a renewable energy company, today announced the achievement of two major regulatory milestones for the Western GeoPower Unit 1 project at The Geysers geothermal field in California, with the receipt of approvals for both the Environmental Document and the Conditional Use Permit.

The unanimous approvals were granted during a public hearing by the Sonoma County Board of Zoning Adjustments for the construction and development of a 38.5 Megawatt (gross) geothermal power plant, wellfield and steam gathering system at the Company's leasehold at The Geysers. Sonoma County is the Lead Agency under the California Environmental Quality Act for projects of under 50 Megawatts capacity being developed within the county.

"This is the first geothermal power plant to be permitted at The Geysers Geothermal Field in 21 years," said Sigrid Swedenborg, Sonoma County Land Use Planner for the project. "It is an exciting project for Sonoma County and meets our General Plan policies to promote renewable energy generation systems."

The power will be purchased, pursuant to a previously announced power purchase agreement, by the Northern California Power Agency, a non-profit joint powers agency that provides electricity generated from environmentally responsible sources to its member communities in Northern and Central California. The power will also help California reach the Renewable Portfolio Standard of supplying 20% of the State's power from renewable energy sources by 2010.

About Western GeoPower Corp.
Western GeoPower Corp. is a renewable energy company dedicated to the development of geothermal energy projects for the delivery of clean, sustainable, baseload electricity generation. The Company is developing The Western GeoPower Unit 1 geothermal power plant at The Geysers Geothermal Field in Sonoma County, California, United States; the South Brawley geothermal project in Imperial County, California, United States; and the South Meager geothermal project in British Columbia, Canada.


SOURCE: Western GeoPower Corp.
Western GeoPower Corp.
Nicole Robson
Marketing and Media
(604) 662-3338 or US/Canada Toll Free: 1-866-662-3322
Email: info@geopower.ca
Investor Relations: ir@geopower.ca


 


Geysers Geothermal Association Website (This page updated February 15, 2010)
All rights reserved. © 2010, Dorothy Beebee